Virtue Road closing til 2022

Virtue Road will be closed to through traffic beginning the week of Monday, Jan. 11. The closure will last for about 15 months until spring 2022.

Construction will take place in two phases. The first phase, scheduled for January through December 2021, is from Kingston Pike to Needlegrass Lane. The second phase, scheduled for September 2021 through March 2022, is Needlegrass Lane to Vista Brook Lane.

Detour signage and closure barricades will be in place. Homeowners will have access to properties throughout the project but should anticipate delays. A detour map is available at townoffarragut.org/virtueroad.

Construction contractor is Bell & Associates Construction.