TSW exits Farragut planning projects
Board weighs future of newly appointed steering committee
The consulting firm's decision came after the Farragut Board of Mayor and Aldermen's Thursday, Nov. 12, meeting, during which the Board appointed members to the Comprehensive Land Use Plan steering committee.
According to Town staff, the contract terminations nullified those appointments.
With the planning projects now in limbo, three Board members and Town staff discussed the future of the steering committee and
possible alternatives during a workshop Thursday, Nov. 19.
TSW canceling the contracts means the "Town doesn't have TSW's support on what we're doing," North Ward Alderman Larry Segrest said.
In a statement to the Town, a TSW spokesman said, "After listening to the discussion, it seems there is significant uncertainty about whether these planning efforts should continue at this time."
TSW added that it believes "the best course is to step back rather than have the Town continue investing
resources in plans that may not have the support needed to move forward.
"This was not an easy decision, and we are disappointed that we could not move the projects forward," the firm stated.
In light of TSW's decision, Vice Mayor Greg Wiberley and North Ward Aldermen Segrest and Joey Ruffalo considered several options for moving forward.
"We could do nothing; we could do the CLUP only; we could do traffic first; or we could do them together," Segrest said.
He added that the Board could re-energize and rename the committee or do away with it.
Segrest suggested examining how future development and land-use decisions would affect traffic.
"If you're going to build stuff here and there and everywhere, what will be the impact on traffic?" Segrest asked. "That's the kind of conversations that I was having."
Town director of Public Services Chris Sheffield questioned what the Board hoped to accomplish.
"What are we trying to achieve here today?" Sheffield asked. "What's the objective? We want to help you drive this train, but I don't know that any of us understand what we're trying to achieve."
Town Human Resources director Michelle Pence suggested the Board consider waiting until the next fiscal year before taking action.
Wiberley suggested continuing with the current CLUP and making minimal changes.
"Shouldn't we start with what projects we already have in the works and then move on to what to do with traffic?" asked Kimberlie Parks, one of the appointed steering committee members.
Board members pointed out that only a few undeveloped parcels remain in Town, but Sheffield warned that
focusing solely on those parcels in the CLUP could leave Farragut "woefully unprepared."
Community Development director Mark Shipley said existing shopping centers or businesses also could change over time. He cited 35 North as an example.
"Is this a massive undertaking like it was in 2012, or is traffic the massive undertaking?" Ruffalo asked.
Pence cautioned against immediately seeking another consultant.
"If we went out to bid now to find a new contractor, I don't think it's probably in our best interest to do that," Pence said. "We need a little time for us to go back out for bids. Let's let it die a little and then go back out, so we're running then off of the 2012 CLUP."